Current Projects
At Buenaventura

FBA-A1 FBA-A2 FBA-A3 FBA-A4 FBA-A5
FBA-A6 FBA-A7 FBA-A8 FBA-A9 FBA-B1
FBA-B2 FBA-B3 FBA-B4 FBA-B5        
Current Projects include:

In 2003:

- Fence Property Line (southern side)
- Water Tank and Water/Irrigation System (Draw water from mountain spring)
- Cut fallen trees into boards for construction of platforms, ranchitos, etc.
- Cut/burn 1 Hectar for farming
- Plant in March for harvest in June
- Plant fruit trees and long-term trees along property perimeter
- Plant beans in November, for harvest in Jan. 2004
- Build 1 wood platform/ranchito on the open patch of land on first mountain ridge

In 2004:

- Tractor/Bulldoze a public access road along the southern edge and up west ridge to connect with current trail that leads to the Granados farm
- Build trails up north ridge and into Buenaventura Ecological Reserve
- Plant in March for Harvest in June
- Build wood platforms, bridges, and railings in Buenaventura Ecological Reserve
- Build a shed/nursery for organic farming project
- Build the first villa (to be used initially as the main house)

In 2005:

- Build 4 villas
- Build a stable, corral and chicken coup
- Begin the construction of the main house (2 story, 4000 square foot structure)

In 2006:

- Build staff quarters
- Completion of the main house by May
- Open for business in November with 5 villas and 2 rooms within the house

In 2007:

- Build 5 additional villas

<<< back to Buenaventura Home